{SAMPLE PROJECTS} SAHARA HOSPITAL [RIYADH]

                   

[5] REHABILITATION OF 6 CONCRETE COLUMNS FOR SAHARA HOSPITAL, RIYADH.

 

Ministry of Health, appointed Bullivant Arabia Ltd. to rehabilitate the 6 concrete columns in the kitchen area of the Sahara Hospital, damaged due to reinforcement corrosion.

The rehabilitation works required a detailed study of the prevailing situation, perform load calculations, design support systems, design new column sections and come up with detailed method statements for each activity on the site to be performed.

The Site Activities for this project included but not limited to.

** Protection of kitchen equipments, walls and floors
** Preliminary inspection of beam locations for designing the support system
** Exposure of footings
** Installation of Support system for the beams and columns with great care.
** Monitoring the movements in the support system using dial gauges
** Chipping around the columns
** Fixing new steel around the columns
** Shotcreting using a proper and effective design mix of grout.
** Waterproofing the Footing top and Column below Ground level
** Backfilling and Compaction
** Re-fixing the electric, water, drainage and gas line (if damaged)
** Concrete floor slab- with proper connection to existing slab and sump pits
** Floor tiles/Marble Fixing
** Painting the columns and repair areas.
 

Click on Image to view  large

Click on Image to view  large

Click on Image to view  large

Click on Image to view  large


 

 

Click on Image to view large


Click on Image to view  large


Click on Image to view  large



Click on Image to view  large

     

Home  About Us  |  Clients  |  Downloads  |  Online Queries  |  Services  |  Contacts

Copyrights reserved by www.bullivantarabia.com [© Powered by: eMiT Solutions]